Center Grove Road Bridge Replacement On Track For Mid-August 2025 Completion
EDWARDSVILLE - Crews have installed a new bridge deck on Center Grove Road as part of an ongoing replacement project east of Esic Drive in Edwardsville, officials said. The construction, which involves replacing a 35-year-old bridge over the Nickel Plate Trail, is progressing well and remains on schedule for completion before mid-August 2025, before the start of the school year. Edwardsville High School, Metro East Lutheran High School, and multiple businesses are located close to the bridge work, which makes it even more important to be completed by that deadline. Keller Construction crews are working six to seven days a week to advance the project despite weather challenges. The trail beneath the bridge will be intermittently closed for safety but will remain open at times for public use. The section of Center Grove Road east of Esic Drive, just past Edwardsville Township Park, is currently closed to all traffic while work continues. The City of Edwardsville advised drivers to